Rhode Island Unveils Two-Step Process for Picking Washington Bridge Contractor

Officials will not when a new bridge will open, but plan to name the firm for the project by June 2025

Gov. Dan McKee speaks at a statehouse news conference on Oct. 15, while Chief of Staff Joseph Almond looks on.
Gov. Dan McKee speaks at a statehouse news conference on Oct. 15, while Chief of Staff Joseph Almond looks on.
Governor’s Office
1 min read
Share
Gov. Dan McKee speaks at a statehouse news conference on Oct. 15, while Chief of Staff Joseph Almond looks on.
Gov. Dan McKee speaks at a statehouse news conference on Oct. 15, while Chief of Staff Joseph Almond looks on.
Governor’s Office
Rhode Island Unveils Two-Step Process for Picking Washington Bridge Contractor
Copy

More than 10 months after the abrupt emergency closing of the westbound Washington Bridge, Rhode Island state officials on Oct. 15 unveiled a revised process for picking a firm to build a new bridge.

Rhode Island transportation officials issued a request for qualifications for companies interested in building the new westbound bridge, and plan to choose two finalists from those applicants in December.

During a Statehouse news conference, state Department of Transportation Director Peter Alviti said the two-step process would result in a highly qualified company and the best design, price and schedule for completing the new span.

“We expect to have the two most qualified companies selected in December through the qualifications process,” Alviti said. “And a final company selected by June (2025), with a notice to proceed to work by July.”

The finalist who is not selected will receive a $1.75 million “stipend” for costs associated with creating its proposal. After a previous RFP failed to attract any bids, the governor’s office said it learned that companies are often discouraged from making such bids due to the expense.

Gov. Dan McKee conceded that the previous RFP process could have been better, and said he recognizes that businesses and motorists are still dealing with the impact of closing the westbound bridge last December.

McKee declined to estimate when a new bridge might open. Previous plans called for a new bridge by the fall of 2026, which now appears unlikely.

This story was reported by The Public’s Radio. You can read the entire story here.

We highlight a few of the many events happening across the Community Libraries of Providence – from a jug band ensemble to a PechaKucha night. Plus: what they’re reading at Rocheambeau Library’s banned books club
Former Majority Leader Pearson says other senators sparked his falling out with Ruggerio
But Rhode Island Attorney General Peter Neronha calls the governor’s plan “half-baked”
List of short- and long-term strategies comes a day before Anchor Medical Associates closes Warwick office
Job growth, wage increases to slow as prices surge