Overnight Lane Closures Start on Washington Bridge to Install Weight Monitors

Crews will close the right and center lanes on the section of Interstate 195 spanning the Seekonk River Tuesday, Wednesday and Thursday from 9 p.m. to 5 p.m. Lanes will again be closed Sunday Feb. 23, through Thursday, Feb. 27.
Crews will close the right and center lanes on the section of Interstate 195 spanning the Seekonk River Tuesday, Wednesday and Thursday from 9 p.m. to 5 p.m. Lanes will again be closed Sunday Feb. 23, through Thursday, Feb. 27.
David Lawlor
Share
Crews will close the right and center lanes on the section of Interstate 195 spanning the Seekonk River Tuesday, Wednesday and Thursday from 9 p.m. to 5 p.m. Lanes will again be closed Sunday Feb. 23, through Thursday, Feb. 27.
Crews will close the right and center lanes on the section of Interstate 195 spanning the Seekonk River Tuesday, Wednesday and Thursday from 9 p.m. to 5 p.m. Lanes will again be closed Sunday Feb. 23, through Thursday, Feb. 27.
David Lawlor
Overnight Lane Closures Start on Washington Bridge to Install Weight Monitors
Copy

The Rhode Island Department of Transportation (RIDOT) plans to start overnight closures of two lanes on the eastbound Washington Bridge on Tuesday to install electrical cables meant to keep tabs on the structural health of the highway.

Crews will close the right and center lanes on the section of Interstate 195 spanning the Seekonk River on Tuesday, Wednesday and Thursday from 9 p.m. to 5 p.m. Lanes will again be closed Sunday, Feb. 23, through Thursday, Feb. 27.

Earlier this month, RIDOT began closing up to two lanes of travel in both directions overnight on Interstate 195 near the main Iway Bridge, also known as the Providence River Bridge. Drivers can expect those closures to continue Tuesday through Thursday nights from 9 p.m. to 5 a.m.

RIDOT paid $2.8 million last May to Swiss-based technology company Kistler to install sensors meant to monitor traffic volumes, vehicle weights and axle loads, vehicle distances, and vehicle classes that cross the bridge.

The eastbound span, constructed in 2008, was converted to take on western traffic days after the state closed the western Washington Bridge in December 2023 when engineers discovered broken anchor rods that put the span at risk of collapse.

State officials say the new weight monitoring system is being placed as a precaution and that the bridge can handle the additional traffic until a new highway is built.

The state plans to award the contract to rebuild the westbound bridge by June 6, 2025.

This article was originally published by the Rhode Island Current.

From her Pawtucket mill studio to an upcoming solo show at Boston’s Gallery NAGA, multi-media artist Kirstin Lamb reflects on her journey, inspirations, and the intricate dot-based paintings that blend Impressionism, cross-stitch, and digital design
The strike that began May 15 forced the Providence psychiatric hospital to close roughly half its beds
After multiple bat sightings at the Friendship Street building, Rhode Island’s Department of Children, Youth and Families shifted to remote work. Union leaders say the infestation highlights deeper health and safety issues as the state weighs renewing the lease
A coalition of 21 Democratic attorneys general — including those from Rhode Island, Massachusetts, and Connecticut — says the Trump administration is unlawfully restricting over $1 billion in VOCA grants, threatening support for crime victims and survivors